Phase Two

Below you will find information on the progress of each of the projects in Phase Two

Name of Site/BuildDurationIntended Start DateIntended Finish Date
Albanwood 48 Weeks 09/06/08 08/05/09
Burydale 48 Weeks 01/09/08 31/07/09
Fleetville 27 Weeks 24/03/08 26/09/08
Otley 26 Weeks 08/09/08 06/03/09
Rainbow 30 Weeks 17/03/08 10/10/08
Sir Frederic Osborn 43 Weeks 16/06/08 10/04/09
Stanfield 45 Weeks 28/07/08 05/06/09