Below you will find information on the progress of each of the projects in phase one| Name of Site/Build | Duration | Intended Start Date | Intended Finish Date |
|---|---|---|---|
| Burymill | 30 Weeks | 06/08/07 | 29/02/08 |
| Crossbrook | 31 Weeks | 25/06/07 | 25/01/08 |
| Furzehill | 56 Weeks | 06/08/07 | 29/08/08 |
| Stevenage children's home 1 | 39 Weeks | 03/09/07 | 22/07/08 |
| The Pines | 60 Weeks | 27/08/07 | 17/10/08 |
| The Barns of Baldock | 52 Weeks | 16/07/07 | 11/08/08 |
| Woodland View | 45 Weeks | 30/07/07 | 21/07/08 |
Burymill
Work began in August 2007
Crossbrook
Work began in June 2007
Furzehill
Work began in August 2007
Stevenage children's home 1
Work began in September 2007
The Barns of Baldock
Work began in July 2007
The Pines
Work began in August 2007
Woodland View
Work began in July 2007